Building Update
Walls should be painted by end of week. Work on floors should start next Monday. Ceiling fixtures. etc. will be installed after painting is finished. Trim work will be after flooring.
Blacktop for driveway and parking lot will begin shortly.
We will be responsible for carpentry work: cabinets in classrooms, office, and sacristy; bookshelves and storage. David Harig has offerred to oversee the work. That will be done after we take possession of the building.
We are looking for kitchen equipment, office furnishings, phones, etc. We will equip the building as best we can with what we have on hand.